Scope of chapter; definitions
The term “military construction” as used in this chapter or any other provision of law includes any construction, development, conversion, or extension of any kind carried out with respect to a military installation, whether to satisfy temporary or permanent requirements, or any acquisition of land or construction of a defense access road (as described in section 210 of title 23).
A military construction project includes all military construction work, or any contribution authorized by this chapter, necessary to produce a complete and usable facility or a complete and usable improvement to an existing facility (or to produce such portion of a complete and usable facility or improvement as is specifically authorized by law).
In this chapter and chapter 173 of this title:
The term “appropriate committees of Congress” means the congressional defense committees and, with respect to any project to be carried out by, or for the use of, an intelligence component of the Department of Defense, the Permanent Select Committee on Intelligence of the House of Representatives and the Select Committee on Intelligence of the Senate.
The term “facility” means a building, structure, or other improvement to real property.
The term “life-cycle cost-effective”, with respect to a project, product, or measure, means that the sum of the present values of investment costs, capital costs, installation costs, energy costs, operating costs, maintenance costs, and replacement costs, as estimated for the lifetime of the project, product, or measure, does not exceed the base case (current or standard) for the practice, product, or measure.
The term “military installation” means a base, camp, post, station, yard, center, or other activity under the jurisdiction of the Secretary of a military department or, in the case of an activity in a foreign country, under the operational control of the Secretary of a military department or the Secretary of Defense, without regard to the duration of operational control.
The term “Secretary concerned” includes the Secretary of Defense with respect to matters concerning the Defense Agencies.
This chapter (other than sections 2830,1
Source
(Added Pub. L. 97–214, § 2(a),Notes
References in Text
Amendments
Effective Date
Except as provided in subsection (b), the amendments made by this Act [see Short Title of 1982 Amendment note below] shall take effect on
The amendment made by section 4 [amending section 138(f)(1) [now 114(b)] of this title] shall apply with respect to funds appropriated for fiscal years beginning after
Short Title of 1982 Amendment
Transfer of Functions
Pilot Program To Support Combatant Command Military Construction Priorities
Pilot Program.—
The Secretary of Defense shall conduct a pilot program to evaluate the usefulness of reserving a portion of the military construction funds of the military departments to help the combatant commands satisfy their military construction priorities in a timely manner.
Location.—
The Secretary of Defense shall conduct the pilot program for the benefit of the United States Indo-Pacific Command in the area of responsibility of the United States Indo-Pacific Command.
Required Investment.—
For each fiscal year during which the pilot program is conducted, the Secretary of Defense shall reserve to carry out military construction projects under the pilot program an amount equal to 10 percent of the total amount authorized to be appropriated for military construction projects by titles XXI, XXII, and XXIII of the Military Construction Authorization Act for that fiscal year.
Commencement and Duration.—
Commencement.—
The Secretary of Defense shall commence the pilot program no later than
Duration.—
The pilot program shall be in effect for the fiscal year in which the Secretary commences the pilot program, as described in paragraph (1), and the subsequent two fiscal years. Any construction commenced under the pilot program before the expiration date may continue to completion.
Progress Report.—
Not later than February 15 of the final fiscal year of the pilot program, the Secretary of Defense shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report evaluating the success of the pilot program in improving the timeliness of the United States Indo-Pacific Command in achieving its military construction priorities. The Secretary shall include in the report—
an evaluation of the likely positive and negative impacts were the pilot program extended or made permanent and, if extended or made permanent, the likely positive and negative impacts of expansion to cover all or additional combatant commands; and
the recommendations of the Secretary regarding whether the pilot program should be extended or made permanent and expanded.”
Permitting Machine Room-Less Elevators in Department of Defense Facilities
In General.—
The Secretary of Defense shall issue modifications to all relevant construction and facilities specifications to ensure that machine room-less elevators (MRLs) are not prohibited in buildings and facilities throughout the Department of Defense, including modifications to the Unified Facilities Guide Specifications (UFGS), the Naval Facilities Engineering Command Interim Technical Guidance, and the Army Corps of Engineers Engineering and Construction Bulletin.
Conforming to Best Practices.—
In addition to the modifications required under subsection (a), the Secretary may issue further modifications to conform generally with commercial best practices as reflected in the safety code for elevators and escalators as issued by the American Society of Mechanical Engineers.
Deadlines.—
The Secretary shall promulgate interim MRL standards not later than 180 days after the date of the enactment of this Act [
Report.—
Not later than 1 year after the date of the enactment of this Act, the Secretary shall issue a report to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] on the integration and utilization of MRLs, including information on quantity, location, problems, and successes.”