Coal conversion and allocation
Powerplant and fuel burning installations
The Federal Energy Administrator—
shall, by order, prohibit any powerplant, and
may, by order, prohibit any major fuel burning installation, other than a powerplant,
from burning natural gas or petroleum products as its primary energy source, if the requirements of subsection (b) of this section are met and if (A) the Federal Energy Administrator determines such powerplant or installation on
Prerequisites to issuance or effectiveness of orders prohibiting use of natural gas or petroleum products as primary energy source
The requirements referred to in subsection (a) of this section are as follows:
An order under subsection (a) of this section may not be issued with respect to a powerplant or installation unless the Federal Energy Administrator finds (A) that the burning of coal by such plant or installation, in lieu of petroleum products or natural gas, is practicable and consistent with the purposes of this chapter, (B) that coal and coal transportation facilities will be available during the period the order is in effect, and (C) in the case of a powerplant, that the prohibition under subsection (a) of this section will not impair the reliability of service in the area served by such plant. Such an order shall be rescinded or modified to the extent the Federal Energy Administrator determines that any requirement described in subparagraph (A), (B), or (C) of this paragraph is no longer met; and such an order may at any time be modified if the Federal Energy Administrator determines that such order, as modified, complies with the requirements of this section.
Before issuing an order under subsection (a) of this section which is applicable to a powerplant or installation for a period ending on or before
An order described in subparagraph (A) of this paragraph shall not become effective until the date which the Administrator of the Environmental Protection Agency certifies pursuant to section 1857c–10(d)(1)(A) 1
Before issuing an order under subsection (a) of this section which is applicable to a powerplant or installation after
An order (or modification thereof) described in subparagraph (A) of this paragraph shall not become effective until (i) the Administrator of the Environmental Protection Agency notifies the Federal Energy Administrator under section 1857c–10(d)(1)(B) 1 of title 42 that such plant or installation will be able on and after
Construction and design of powerplants or other major fuel burning installations
Allocation of coal
Definitions
For purposes of this section:
The term “powerplant” means a fossil-fuel fired electric generating unit which produces electric power for purposes of sale or exchange.
The term “coal” includes coal derivatives.
Expiration of authority; effective dates
Authority to issue orders or rules under subsections (a) through (d) of this section shall expire at midnight,
Authority to amend, repeal, rescind, modify, or enforce such rules or orders shall expire at midnight,
Source
(Pub. L. 93–319, § 2,Notes
References in Text
Amendments
Transfer of Functions
Compliance Orders
Section 119 of such Act [section 1857c–10 of Title 42, The Public Health and Welfare] is hereby repealed. All references to such section 119 [section 1857c–10 of Title 42] or subsections thereof in section 2 of the Energy Supply and Environmental Coordination Act of 1974 (Public Law 93–319) [this section] or any amendment thereto, or any subsequent enactment which supersedes such Act [Pub. L. 93–319,
In the case of any major stationary source to which any requirement is applicable under section 113(d)(5)(B) of the Clean Air Act [section 7413(d)(5)(B) of Title 42] and for which certification is required under section 2 of the Energy Supply and Environmental Coordination Act of 1974 [this section] or any amendment thereto, or any subsequent enactment which supersedes such Act [Pub. L. 93–319], the Administrator of the Environmental Protection Agency shall certify the date which he determines is the earliest date that such source will be able to comply with all such requirements. In the case of any plant or installation which the Administrator of the Environmental Protection Agency determines (after consultation with the State) will not be subject to an order under section 113(d) of the Clean Air Act [section 7413(d) of Title 42] and for which certification is required under section 2 of the Energy Supply and Environmental Coordination Act of 1974 [this section] or any amendment thereto, or any subsequent enactment which supersedes such Act [Pub. L. 93–319], the Administrator of the Environmental Protection Agency shall certify the date which he determines is the earliest date that such plant or installation will be able to burn coal in compliance with all applicable emission limitations under the implementation plan.
Any certification required under section 2 of the Energy Supply and Environmental Coordination Act of 1974 [this section] or any amendment thereto, or any subsequent enactment which supersedes such Act [Pub. L. 93–319], or under this subsection may be provided in an order under section 113(d) of the Clean Air Act [section 7413(d) of Title 42].”