Acquisition of sites and buildings for diplomatic and consular establishments; allotment of space; credit of payments without regard to limitations of amounts
Authority of Secretary of State
Payments from other than appropriated funds for acquisition of property
Authorization for improvements and construction
Source
(May 7, 1926, ch. 250, § 1, 44 Stat. 403; May 29, 1928, ch. 876, § 1, 45 Stat. 971; Pub. L. 88–94, § 2(b),Notes
Editorial Notes
Amendments
Statutory Notes and Related Subsidiaries
Standard Design in Capital Construction
Sense of Congress.—
It is the sense of Congress that the Department’s Bureau of Overseas Building Operations (OBO) or successor office should give appropriate consideration to standardization in construction, in which each new United States embassy and consulate starts with a standard design and keeps customization to a minimum.
Consultation.—
The Secretary shall carry out any new United States embassy compound or new consulate compound project that utilizes a non-standard design, including those projects that are in the design or pre-design phase as of the date of the enactment of this Act [
A comparison of the estimated full lifecycle costs of the project to the estimated full lifecycle costs of such project if it were to use a standard design.
A comparison of the estimated completion date of such project to the estimated completion date of such project if it were to use a standard design.
A comparison of the security of the completed project to the security of such completed project if it were to use a standard design.
A justification for the Secretary’s selection of a non-standard design over a standard design for such project.
A written explanation if any of the documentation necessary to support the comparisons and justification, as the case may be, described in paragraphs (1) through (4) cannot be provided.
Sunset.—
The consultation requirement under subsection (b) shall expire on the date that is 4 years after the date of the enactment of this Act.”
Value Engineering and Risk Assessment
Findings.—
Congress makes the following findings:
Federal departments and agencies are required to use value engineering (VE) as a management tool, where appropriate, to reduce program and acquisition costs pursuant to OMB Circular A–131, Value Engineering, dated
OBO has a Policy Directive and Standard Operation Procedure, dated
Notification Requirements.—
Submission to authorizing committees.—
Any notification that includes the allocation of capital construction and maintenance funds shall be submitted to the appropriate congressional committees.
Requirement to confirm completion of value engineering and risk assessment studies.—
The notifications required under paragraph (1) shall include confirmation that the Department has completed the requisite VE and risk management process described in subsection (a), or applicable successor process.
Reporting and Briefing Requirements.—
The Secretary shall provide to the appropriate congressional committees upon request—
a description of each risk management study referred to in subsection (a)(2) and a table detailing which recommendations related to each such study were accepted and which were rejected; and
a report or briefing detailing the rationale for not implementing any such recommendations that may otherwise yield significant cost savings to the Department if implemented.”