Alaska natural gas pipeline

Not later than 180 days after

August 8, 2005
, and every 180 days thereafter until the Alaska natural gas pipeline commences operation, the Federal Energy Regulatory Commission shall submit to Congress a report describing—

(1)

the progress made in licensing and constructing the pipeline; and

(2)

any issue impeding that progress.