Identification of flood-prone areas
Publication of information; establishment of flood-risk zones; estimates of flood-caused loss
The Administrator is authorized to consult with, receive information from, and enter into any agreements or other arrangements with the Secretaries of the Army, the Interior, Agriculture, and Commerce, the Tennessee Valley Authority, and the heads of other Federal departments or agencies, on a reimbursement basis, or with the head of any State or local agency, or enter into contracts with any persons or private firms, in order that he may—
identify and publish information with respect to all flood plain areas, including coastal areas located in the United States, which has special flood hazards, within five years following
establish or update flood-risk zone data in all such areas, and make estimates with respect to the rates of probable flood caused loss for the various flood risk zones for each of these areas until the date specified in section 4026 of this title.
Accelerated identification of flood-risk zones; authority of Administrator: grants, technical assistance, transactions, and payments
Priority in allocation of manpower and other available resources for identification and mapping of flood hazard areas and flood-risk zones
Plan for bringing communities with flood-risk zones into full program status
Review of flood maps
Updating flood maps
The Administrator shall revise and update any floodplain areas and flood-risk zones—
upon the determination of the Administrator, according to the assessment under subsection (e), that revision and updating are necessary for the areas and zones; or
upon the request from any State or local government stating that specific floodplain areas or flood-risk zones in the State or locality need revision or updating, if sufficient technical data justifying the request is submitted and the unit of government making the request agrees to provide funds in an amount determined by the Administrator.
Availability of flood maps
Notification of flood map changes
Compendia of flood map changes
Provision of information
Source
(Pub. L. 90–448, title XIII, § 1360,Notes
References in Text
Codification
Amendments
Effective Date
Transfer of Functions
Flood Protection Structure Accreditation Task Force
Definitions.—
In this section—
the term ‘flood protection structure accreditation requirements’ means the requirements established under section 65.10 of title 44, Code of Federal Regulations, for levee systems to be recognized on maps created for purposes of the National Flood Insurance Program;
the term ‘National Committee on Levee Safety’ means the Committee on Levee Safety established under section 9003 of the National Levee Safety Act of 2007 (33 U.S.C. 3302); and
the term ‘task force’ means the Flood Protection Structure Accreditation Task Force established under subsection (b).
Establishment.—
In general.—
The Administrator and the Secretary of the Army, acting through the Chief of Engineers, in cooperation with the National Committee on Levee Safety, shall jointly establish a Flood Protection Structure Accreditation Task Force.
Duties.—
Developing process.—
The task force shall develop a process to better align the information and data collected by or for the Corps of Engineers under the Inspection of Completed Works Program with the flood protection structure accreditation requirements so that—
information and data collected for either purpose can be used interchangeably; and
information and data collected by or for the Corps of Engineers under the Inspection of Completed Works Program is sufficient to satisfy the flood protection structure accreditation requirements.
Gathering recommendations.—
The task force shall gather, and consider in the process developed under subparagraph (A), recommendations from interested persons in each region relating to the information, data, and accreditation requirements described in subparagraph (A).
Considerations.—
In developing the process under paragraph (2), the task force shall consider changes to—
the information and data collected by or for the Corps of Engineers under the Inspection of Completed Works Program; and
the flood protection structure accreditation requirements.
Rule of construction.—
Nothing in this section shall be construed to require a reduction in the level of public safety and flood control provided by accredited levees, as determined by the Administrator for purposes of this section.
Implementation.—
The Administrator and the Secretary of the Army, acting through the Chief of Engineers, shall implement the process developed by the task force under subsection (b) not later than 1 year after the date of enactment of this Act [
Reports.—
The Administrator and the Secretary of the Army, acting through the Chief of Engineers, in cooperation with the National Committee on Levee Safety, shall jointly submit to the Committee on Banking, Housing, and Urban Affairs and the Committee on Environment and Public Works of the Senate and the Committee on Financial Services, the Committee on Transportation and Infrastructure, and the Committee on Natural Resources of the House of Representatives reports concerning the activities of the task force and the implementation of the process developed by the task force under subsection (b), including—
an interim report, not later than 180 days after the date of enactment of this Act [
a final report, not later than 1 year after the date of enactment of this Act.
Termination.—
The task force shall terminate on the date of submission of the report under subsection (d)(2).”